Guide
Turnkey fabrication quotes: what to send to get a firm price
Updated
Most slow, vague and wildly different fabrication quotes come from the same cause: the enquiry did not contain enough to price from.
The checklist
- Drawings or files. DXF for flat profiles, STEP for 3D, plus a dimensioned drawing. A PDF alone means someone redraws it.
- Material and grade. Or a description of the environment and the loads so the fabricator can advise.
- Thickness and section sizes. On the drawing, not in the covering email.
- Tolerances. Tight where it matters, general everywhere else, and say which is which.
- Welding requirements. Whether the welds are structural, whether procedures and welders must be qualified, and any inspection or testing required.
- Finish. Including a RAL or BS colour reference where relevant.
- Quantity, and whether repeats are likely.
- Delivery address and access. Plus whether installation is needed and what is on site to unload.
- The date you need it. A real one, including whether the finishing lead time is inside it.
If you do not have drawings
You still have options, and saying so honestly is better than sending a vague enquiry. A photograph with a tape measure in it, a sample or the broken original, or a marked-up sketch with the critical dimensions will all get you a sensible conversation.
Many fabricators offer design and build, producing the drawings as part of the job. Turnkey fabrication quotes go one step further and include the installation. It costs more than making to drawings, and it is often quicker and cheaper than commissioning drawings separately and then discovering they are not manufacturable.
Turnkey fabrication quotes
A turnkey quote prices the whole job from one firm: design or detailing, fabrication, finishing, delivery and installation, often with the survey before it.
Ask for each stage to be priced on its own line, so you can see what the installation and the finishing subcontract add. Say who produces and signs off the drawings. If the steel is structural, the turnkey firm has to be certified for the execution class your engineer sets.
Sheet metal fabrication quotes
For sheet metal quotes, send a flat DXF or STEP model with the bend lines. Add material and thickness, the inside bend radius if it matters, the quantity and the finish. Many sheet metal shops quote cut and folded parts straight from the file. A one-off still carries the programming and press brake setup, so give a realistic batch size.
Steel and pipework fabrication quotes
For steel fabrication and pipework quotes, add the section sizes and grade, and the weld standard or procedure if one applies. Add any pressure, test or certification requirement for the pipework, the coating, and the site access for delivery or installation. A fabrication shop can only quote a fixed price on what it can see in the enquiry.
Questions worth asking every quote
- Is this a fixed price or an estimate, and what would change it?
- Is material included at today's price, and for how long is the quote valid?
- Is finishing included, and is its lead time inside your quoted delivery date?
- Who is responsible if the part does not fit: you, or the drawings I supplied?
- What certification do you hold for this kind of work, and can I see it?
- What are the payment terms, and is a deposit required for material?
Material prices move. A quote that was firm three months ago may not be firm today, and a fabricator who tells you that up front is being straight with you rather than hedging.
Comparing quotes fairly
Put every quote against the same specification before comparing totals. The common differences are material grade, whether finishing and delivery are included, tolerance assumptions and what the price does if the drawings change.
A quote that is twenty per cent cheaper because it assumed a lighter grade and no galvanising is not cheaper: it is a different part. Where structural steelwork is involved, also compare what the fabricator is certified to produce, and check it against what your designer specified.